Total Savings:
20%Electricity Savings (kWh): | 241,471 | 22% | |
Natural Gas Savings (Therms): | 0 | 0% | |
Overall Energy Savings (Mbtu): | 824 | 20% | |
Utility Cost Savings ($): | $13,337 | 20% | |
Estimated Project Cost ($): | $64,070 | 4.80 | yrs. (Payback) |
Available Utility Incentives($): | $14,294 | 22% | of Proj. Cost |
Net Cost w/Incentives ($): | $49,776 | 3.73 | yrs. (Payback) |
Date Completed: November 2009
Client: City of Webster Groves, MO
Size: 35,274 sq. ft.
Type of Construction: Existing
Service: Energy Audit
Facility Type: Government
The Webster Groves City Hall includes administrative offices, the Council Chamber, police department and fire department with portions of the facility operating 24 hours per day, 7 days per week. The combination of building uses and multiple additions and renovations to the original building made this project a challenge, but many effective upgrade options were identified.