Sparta Lincoln Middle School

Total Savings:

43%
Electricity Savings (kWh): 494,814 42%
Natural Gas Savings (Therms): 8,169 52%
Overall Energy Savings (Mbtu): 2,505 45%
Utility Cost Savings ($): $43,905 43%
Estimated Project Cost ($): $98,476 2.24 yrs. (Payback)
Available Utility Incentives($): $71,518 73% of Proj. Cost
Net Cost w/Incentives ($): $26,958 0.61 yrs. (Payback)

Date Completed: April 2014
Client: Sparta Community Unit School District #140
Size: 72,781 sq. ft.
Type of Construction: Existing
Service: Energy Audit
Facility Type: Education K-12

CxE performed an energy audit for this facility to identify measures to reduce energy usage, improve the indoor environmental quality, and save the school district money on operating costs. Measures demonstrate a simple payback of 2.24 years, with a payback of just over six months when the potential incentives are applied.