Scott Elementary School
Total Savings:
43%Electricity Savings (kWh): | 625,688 | 38% | |
Natural Gas Savings (Therms): | 40,854 | 58% | |
Overall Energy Savings (Mbtu): | 6,220 | 49% | |
Utility Cost Savings ($): | $93,800 | 43% | |
Estimated Project Cost ($): | $206,736 | 2.20 | Payback (yrs.) |
IEN Incentives Available ($): | $42,393 | 21% | of Proj. Cost |
Net Cost w/Incentives ($): | $164,343 | 1.75 | Payback (yrs.) |
Date Completed: September 2017
Client: Mascoutah CUSD #19
Size: 97,000 sq. ft.
Type of Construction: Existing
Service: Energy Audit, Control System Upgrade
Facility Type: K-12 Facilities
This elementary school on Scott Air Force Base is one floor and houses classrooms for preschool through grades five, a gymnasium, a multipurpose room, cafeteria and food service, a library and computer lab, and administrative and supporting office areas.